Marchwood Power Ltd
Marchwood Power Ltd
 
Construction
   
   
Photogallery -
Construction progress

1 click to enlarge Dec 07
2 click to enlarge  
3 click to enlarge  
4 click to enlarge  
5 click to enlarge  
6 click to enlarge Feb 08
7 click to enlarge  
8 click to enlarge  
9 click to enlarge  
10 click to enlarge  
11 click to enlarge Jul 08
12 click to enlarge  
13 click to enlarge  
14 click to enlarge  
15 click to enlarge  

Photos will be updated on a quarterly basis during construction of the plant.
 
Conditions of Contract for suppliers

Main construction of the new plant started in January 2007 and after a period of commissioning and comprehensive testing, the power station entered commercial operation on December 10th 2009. The facility was built under an Engineering, Procurement and Construction (EPC) contract by a consortium of Siemens plc and Siemens AG. Siemens has a long track record in building CCGT plants in the UK and overseas.


During construction of the power station and the underground gas pipeline (linking Marchwood Power to the country's national gas transmission network) a full range of measures were implemented to minimise the impact of the work on the local community. All contractors working on the site and the pipeline were required to follow best construction, safety management practices to comply with all planning conditions and local statutory requirements including health and safety.


A comprehensive Traffic Impact Assessment was conducted in accordance with the planning consents process as civil, mechanical and some heavy load traffic feature during the construction phase. To limit the impact of the construction traffic, transportation of major equipment to the site entered the site via Marchwood Military Port on Southampton Water.


At every stage during construction of the plant, Marchwood Power had worked closely with the local authorities and the Environment Agency to ensure that the construction impact was carefully managed and in accordance to the planning conditions.


As part of the construction phase a 23.5km underground gas pipeline was installed to connect the plant to the main gas network at Lockerly. The pipeline crosses farm land, the M27 and other main roads as well as the rail network.


As the new plant has been built on the site of a former power station, where possible the facility has used existing on-site energy infrastructure.

 

[BACK TO TOP]

 

Printer Friendly Version

 
 
Marchwood Power Limited, Oceanic Way, Marchwood Industrial Park , Marchwood , SO40 4BD.
Tel: 02380 527999 Fax: 02380 527998